![]() To show the project summary task, select the Project Summary Task check box in the Show/Hide group on the Options tab. ![]() Want to see the project-level summary task? You can also choose to show the project summary task, which is the very top row in the list of your project’s tasks, and represents how all summary tasks and subtasks roll up to the project level. The summary task begins with the earliest start date from its subtasks, and ends with the latest finish date from its subtasks. ![]() When you are using automatic scheduling, the duration, start, and finish dates for a summary task are driven by the subtasks listed below the summary task. Tip: Project not currently open for editing? Click Projects on the Quick Launch, click the name of your project in the list on the Project Center, and then, on the Project tab or the Task tab, click Edit.